New car preparation center Garching

Project type

New commercial building

Date

2013-2014

Location

Garching near Munich

New construction of a processing center with 40 processing bays, sheet metal shop and paint shop, administration building with cafeteria, gas station and car wash

Bored pile foundation with 1,100 bored piles; vibratory compaction of concrete/gravel

Foundation slab with increased flatness tolerances according to DIN 18202-3; ventilated metal panel facade, sandwich facade elements

Construction period: 8 months

Gross floor area of the hall: approx. 6,500 m²
Gross floor area of the administration building: approx. 1,800 m²
Gross floor area of the unheated warehouse: approx. 1,000 m²

Service phases 1-2, 3-8
Cost volume: approx. €7.5 million

Client:
FABCO GmbH & Co. KG