New car preparation center Garching
Project type
New commercial building
Date
2013-2014
Location
Garching near Munich
New construction of a processing center with 40 processing bays, sheet metal shop and paint shop, administration building with cafeteria, gas station and car wash
Bored pile foundation with 1,100 bored piles; vibratory compaction of concrete/gravel
Foundation slab with increased flatness tolerances according to DIN 18202-3; ventilated metal panel facade, sandwich facade elements
Construction period: 8 months
Gross floor area of the hall: approx. 6,500 m²
Gross floor area of the administration building: approx. 1,800 m²
Gross floor area of the unheated warehouse: approx. 1,000 m²
Service phases 1-2, 3-8
Cost volume: approx. €7.5 million
Client:
FABCO GmbH & Co. KG